Whose job it is, and when it changes hands
The developer’s
Building it
Roads, stormwater, parks and streetscapes the approval asks for.
BondUncompleted works bond lets the plan seal before the last works are done.
Still the developer’s
Looking after it, usually 12 months
Council has accepted the works, but the developer maintains them and repairs any faults. The letter says how long.
BondMaintenance bond held by council until the end.
Council’s
For good
Council repairs and maintains it from here.
BondBond back with the letter.
What on maintenance means
Once the works the approval’s conditions ask for are built, the developer asks council for an on-maintenance inspection. In Brisbane the request goes in with the as-constructed plans and certification. If the works pass, council invoices the maintenance bond where the approval asks for one, and the on-maintenance letter that follows marks the start of the maintenance period.
Councils date it from different things. Moreton Bay accepts works on maintenance from the latest of three: the successful inspection, the documents, and the bond being lodged. Whatever the council, the letter is the date that counts.
How long the maintenance period is
Usually 12 months, but it varies, and the on-maintenance letter says how long. Through it the developer maintains the works, repairs any faults and, where the approval asks, carries public liability insurance.
Off maintenance
At the end of the period, with any defects fixed, the developer asks for the off-maintenance inspection. Brisbane wants the on-maintenance letter and the maintenance bond receipt with the request, and arranges the inspection within five business days. In Brisbane a defect found at an inspection can mean a reinspection fee.
When the works pass, the off-maintenance letter confirms the approval’s conditions are met and releases the maintenance bond. From then the works are council’s.
The two bonds
The maintenance bond is held through the maintenance period and comes back with the off-maintenance letter.
The uncompleted works bond lets the survey plan be sealed before every work is finished, so lots can title while the last works are built. Brisbane asks for an undertaking that the works will be finished within three months of the plan being sealed. Some councils let it come down, or move across to the maintenance bond, once the works go on maintenance: Logan on request, and Burdekin can transfer it.
Where it goes wrong
Nothing in it moves by itself. Off maintenance happens when the developer asks for it, so a missed date doesn’t fail loudly. If the walk to find defects before off maintenance isn’t done in time, the period runs on: the bond stays with council and the works go on being maintained at the developer’s cost.
And it is never one stage. A development runs many, each with its own letters, dates and bonds, and between them they live in folders, a spreadsheet and somebody’s memory. A letter council still owes is the easiest thing to lose.
Keeping track of it in FRED Planner
Each stage in FRED Planner keeps its dates from council’s letters: on maintenance from the on-maintenance letter, off maintenance from the period it sets, the pre off-maintenance inspection three months before that, and each bond with when it comes back. Forward a letter to your company’s FRED address and it reads it and files it on its stage.
So the stage list shows what’s overdue, what’s coming, and which stages are waiting on council’s letter.

Sources
Councils change their processes. Your approval’s conditions and your council have the final word.
- Brisbane City Council: On and off maintenance approvals
- Brisbane City Council: Bonding of uncompleted works checklist